Sabah's Power Plan Explained: Your Bill and Blackouts to 2035

Last updated: 27 September 2026

What is Sabah's power plan in one paragraph?

SE-RAMP 2040, the Energy Commission of Sabah's 2023 plan, promises blackouts under 100 minutes a year and power for every rural home by 2030, a tariff that pays its own way by 2030, and more than 50% renewable capacity by 2035. In 2021 Sabah had 332 minutes of outages per customer, a 16% reserve margin and 86% of its electricity from gas.

What is SE-RAMP 2040?

SE-RAMP 2040 (Sabah Energy Roadmap and Master Plan 2040) is the state's plan for electricity, published in 2023 by the Energy Commission of Sabah (ECoS). It explains why Sabah's power supply is weak, sets seven targets for 2030 to 2050, and lists the projects meant to get there. The plan is to be reviewed every three years, so its targets may change.

Most of its figures describe 2021. Below, each target is shown with the latest progress we could find, dated, so you can see what has actually happened since.

What are the seven targets, and how far along are they?

SE-RAMP sets five state targets and adopts two national ones. Here they are with the 2021 starting point in the plan and the latest status.

Target (deadline)2021, per SE-RAMPLatest
Power cuts (SAIDI) below 100 minutes a year (end 2030)332.1 minutes226 minutes as of July 2026 (Chief Minister, Sep 2026)
100% rural electrification (end 2030)98.3%96% (ECoS CEO, June 2025; likely a different basis). See rural electrification
"Sustainable" electricity tariff (end 2030)Heavily subsidisedFirst tariff rise since 2014, on 1 Feb 2026
Balanced fuel mix, HHI below 0.5 (end 2035)0.79 (2019)No later official figure found
Renewables above 50% of capacity and 30% of energy (2035)7.3% of energy307 MW from renewables (Bernama, Jul 2026); no official % found
Low-carbon nation, national aim (2040)No carbon inventory yet; one was to be set up in 2024No later update found
Carbon neutrality, national aim (2050)Long-term–

Sabah's renewables target is more ambitious than the national one in the same plan: SE-RAMP compares it with a national target of 40% of capacity and 27% of energy by 2035.

Why does Sabah have so many blackouts?

The short answer: not enough spare generating capacity, and one main power line linking the west and east coasts. SE-RAMP says the reserve margin, the spare capacity above peak demand, fell from 36.0% in 2016 to 16.0% in 2021, against an industry standard of 30% to 35%. (The plan gives two figures for 2021: 16.0% in its reserve-margin chart, p.79, and 17.6% in its SESB quick facts, p.29.) When one plant trips, there is little to replace it, and whole areas go dark. The plan's own path aimed for a 28% margin in 2024–2025; the state government later reported 8% for 2024. The plan also calls the single 275 kV backbone to the east coast a security risk. More in why Sabah has so many power cuts and our Southern Link page.

MeasureSE-RAMP figureLatest figure
Average outage minutes per customer (SAIDI)777.3 (2014), 332.1 (2021)598 (2023) to 226 (July 2026), Chief Minister; SESB gave 207 for 2024
Reserve margin16.0% (2021); planned 28% for 2024–2025, 30–35% by 20308% (2024), 19% (Aug 2026), 26% expected by end 2026
ℹ️ Why the SAIDI numbers don't line up

SAIDI has been counted in different ways. SE-RAMP notes that major incidents were excluded before 2021 and included from 2021, and the figures quoted by SESB and the state government since then do not always match. Treat the trend as more reliable than any single number.

Why did my electricity bill go up?

Because the tariff had not changed since 2014, while the cost of supplying power had risen. For 2022 to 2024 the approved cost of supply was 43.83 sen/kWh, but customers paid an average of 34.52 sen/kWh. The federal government covered the gap with subsidies worth 9.31 sen for every unit, about RM1,760 million over the three years.

From 1 February 2026, SESB raised the average base tariff to 39.70 sen/kWh. Homes pay 22.02 sen/kWh for the first 200 kWh a month and more for higher bands; see the full table on our utilities page, and our tariff and subsidy explainer for worked bill examples.

  • How tariffs are now set: since January 2022 Sabah has used Incentive Based Regulation (IBR). The tariff is reviewed every three years, and fuel-cost changes can be passed through every six months.
  • Where it is heading: SE-RAMP's target is a "sustainable electricity tariff" by the end of 2030, which means less subsidy. The plan says Sabah needs to explore a targeted subsidy programme for lower-income groups (p.108).
  • Old rebate: a 1.20 sen/kWh rebate for homes using under 300 kWh a month ended in June 2018.

Where will Sabah's power come from by 2035?

Today, mostly gas. In 2021, 86% of Sabah's electricity came from natural gas, 6.7% from diesel and fuel oil, and 7.3% from renewables. The plan wants gas down to about 55% and renewables, mainly hydro, up to about 35% by 2035, from a system of 1,805 MW instead of 1,179 MW.

Source2021 share2035 target
Natural gas86.0%55.4%
Hydro4.6%28.6%
Other renewables (solar, biomass, biogas)2.7%6.6%
Battery storage–6.6%
Imports (e.g. from Sarawak)–2.8%
Diesel and fuel oil6.7%–

Source: SE-RAMP 2040, printed p.75. Shares of generation.

Sabah is gas-rich: it had over 11.67 trillion cubic feet of gas reserves in 2019, about 15% of Malaysia's. But in 2019 only 16% of Sabah's gas output went to power; 45% was exported and 37% went to petrochemical plants.

Which projects are being built?

ProjectWhat SE-RAMP (2023) saidStatus as of September 2026
Sarawak–Sabah interconnection (Lawas–Mengalong, 275 kV)30 MW, rising to 50 MW, for 15 yearsLive since 13 Dec 2025, supplying up to 50 MW (Sarawak Energy). See power from Sarawak
Upper (Ulu) Padas hydro180 MW by 2029Re-approved May 2026 as 187.5 MW hydro (by end 2030) plus 150 MWac floating solar (by end 2031)
Southern Link, now the Sabah Southern Madani LinkSecond 275 kV route to Tawau; Phase 2 by 2027Phase 1A (60 km, Mengalong to Upper Padas) 17% built in May 2026, due Sep 2028; Phase 1B (about 270 km to Tawau) not yet dated
Lahad Datu battery storageNew East Coast battery storage, 120 MW, planned for 2023–2025100 MW / 400 MWh inaugurated 12 Dec 2025
Large-scale solar113.9 MW awarded, 50 MW operating (2022); solar kept to 20–22% of peak demand450 MW programme: 200 MW under construction, 250 MW in bidding (Bernama, Jul 2026)
Telekosang hydro 1 and 240 MW, completed Feb 2023Operating
Tawau (Apas Kiri) geothermal30 MW plant abandoned Dec 2018; revival under reviewNo revival announced

SE-RAMP also floats longer-term links to North Kalimantan in Indonesia and Palawan in the Philippines, which would let Sabah trade power across the BIMP-EAGA region. These are ideas, not projects, in the plan.

Who is responsible for delivering the plan?

The Energy Commission of Sabah (ECoS) regulates electricity in the state and wrote the plan. SE-RAMP sets up a Sabah Energy Council chaired by the Chief Minister, with ECoS as its secretariat, to track progress. Sabah Electricity Sdn Bhd (SESB), majority-owned by Tenaga Nasional Berhad, runs the grid and bills customers.

The Chief Minister's September 2026 update on SAIDI and the reserve margin came after a Sabah Energy Council meeting. Our renewable energy page covers the solar, hydro and palm-waste targets in more detail, and our RMK13 page covers the federal plan's 40% renewable capacity target for 2030.

ℹ️ How we checked this page

Every SE-RAMP number was checked against the printed page of the plan. Every "latest" figure comes from a dated 2025–2026 source listed below. Where official figures disagree, we show both.

Frequently asked questions

Q What is SE-RAMP 2040?
SE-RAMP 2040 is the Sabah Energy Roadmap and Master Plan 2040, published in 2023 by the Energy Commission of Sabah (ECoS). It sets seven targets for Sabah's electricity supply, from shorter blackouts and 100% rural electrification by 2030 to more than 50% renewable capacity by 2035 and carbon neutrality by 2050. It is meant to be reviewed every three years.
Q Why did the Sabah electricity tariff go up in 2026?
SESB's average base tariff had stayed at 34.52 sen/kWh since 2014, while the approved cost of supply for 2022–2024 was 43.83 sen/kWh, with federal subsidy covering the gap. From 1 February 2026 the average base tariff rose to 39.70 sen/kWh. SE-RAMP's target is a 'sustainable' tariff by 2030, which means relying less on subsidy.
Q What is SAIDI?
SAIDI (System Average Interruption Duration Index) is the average number of minutes of power cuts each customer has in a year. SE-RAMP recorded 332.1 minutes for 2021 and targets below 100 minutes by the end of 2030. The Chief Minister said in September 2026 that it had fallen to 226 minutes as of July 2026.
Q Is the Sarawak-Sabah power link working?
Yes. Power began flowing on 13 December 2025. In January 2026 Sarawak Energy said it was supplying up to 50 MW to Sabah, with capacity to increase subject to system readiness. SE-RAMP had planned an initial 30 MW rising to 50 MW.
Q When will Upper Padas dam be finished?
SE-RAMP (2023) listed the Upper Padas hydroelectric project at 180 MW for 2029. In May 2026 it was re-approved as a hybrid of 187.5 MW hydro plus 150 MWac floating solar, with the hydro plant due on or before 31 December 2030 and the solar by 31 December 2031.
Sources & References 11 sources

Last verified: 27 September 2026

📮 Free Weekly Newsletter

Get Sabah This Week, free every Thursday

One short email a week on what's happening around Sabah: events, food, and local life. Free to join, and free to leave whenever you like.

One email a week. Unsubscribe anytime. See what’s inside →