Sabah Southern Link Power Line: Route, Cost and Progress (2026)
What is the Sabah Southern Link?
The Sabah Southern Madani Link is a 275 kV power line of about 330 km being built from Mengalong in Sipitang through Upper Padas towards the east coast, giving Sabah a second route between its west and east grids. Phase 1A (60 km to Upper Padas, RM198 million) began in September 2025 and is due on 16 September 2028. The whole project is estimated at close to RM2 billion.
What is the Southern Link?
The Southern Link is a high-voltage (275 kV) transmission line that will run along the south of Sabah, from the west coast grid at Mengalong, Sipitang, through Upper Padas in the interior, to the east coast grid. The state energy plan, SE-RAMP 2040, calls it the Southern Link. It is now called the Sabah Southern Madani Link (SSML). Sabah Electricity (SESB) is building it.
Why does Sabah need it?
Today the west and east coast grids are joined mainly by one line: the 275 kV Kolopis–Segaliud East-West Link. It carries power from the west coast to cover the east coast's shortfall. SE-RAMP calls this sole backbone a security risk in critical need of reinforcement.
The risk is real. On 13 September 2025 a tower on the Kolopis–Segaliud line collapsed in a landslide, and the line was not fully restored until 21 September. See why Sabah has so many power cuts.
According to SE-RAMP, the Southern Link will:
- Complete a loop around the 275 kV backbone, so power can reach the east coast by two routes.
- Give N-1 contingency for sources of power and N-2 contingency for transmission lines: the grid can lose one power source, or two lines, and keep supplying customers.
- Let cheaper west coast power (gas, hydro and imports from Sarawak) replace more costly generation on the east coast.
- Serve as the gateway for the Sabah-Sarawak interconnection at Mengalong.
What is the route and how far along is it?
| Section | Route and length | Status as of September 2026 |
|---|---|---|
| Phase 1A | Mengalong (Sipitang) to Upper Padas (Tenom), about 60 km, double-circuit 275 kV; RM198 million | Construction began 17 September 2025; 17% complete on 26 May 2026; due 16 September 2028 |
| Phase 1B | Upper Padas to Kalumpang, about 270 km | No construction date or completion date published |
| Whole project | About 330 km, Sipitang to the east coast | Estimated close to RM2 billion (The Star, June 2026) |
Sources: The Star, 12 June 2026, quoting SESB; Borneo Post, 13 June 2026; route lengths for Phase 1B and the total from an engineer's column in the Borneo Post, 28 June 2026.
Prime Minister Anwar Ibrahim launched the project at a groundbreaking ceremony in Sipitang on 13 June 2026.
How has the timeline changed?
SE-RAMP, published in 2023, planned Phase 1 (Mengalong to Upper Padas) by 2024 and Phase 2 (Upper Padas to PMU Tawau) by 2027. Neither date was met. The first 60 km section started construction in September 2025 and is now due in September 2028, and the remaining section has no published date.
SE-RAMP estimated in 2023 that about RM2 billion of further transmission and distribution work was needed, including the Southern Link (p.35). In June 2026 The Star reported the SSML alone at close to RM2 billion.
What else connects to it?
- Sarawak power: the Sarawak-Sabah interconnection enters Sabah at Mengalong and has supplied up to 50 MW since 13 December 2025; see power from Sarawak.
- Upper Padas hydro: SE-RAMP says the main intake substation at Upper Padas will connect 357 MW of new hydropower expected by 2030. The Upper Padas dam itself was re-approved in May 2026 as 187.5 MW by end 2030; see renewable energy in Sabah.
- East coast: SE-RAMP says the Tawau end is to be upgraded in line with the Southern Link, and that the Segaliud–Dam Road line is the main supply to Kunak and Semporna.
Frequently asked questions
Q What is the Sabah Southern Madani Link?
Q When will the Southern Link be completed?
Q How much does the Southern Link cost?
Q Will the Southern Link stop blackouts on the east coast?
Sources & References 7 sources
Last verified: 27 September 2026
Latest status
- The Star, 12 Jun 2026: Building a stronger power lifeline for Sabah Phase 1A: 60 km double-circuit 275 kV, Mengalong to Upper Padas, RM198m, started 17 Sep 2025, due 16 Sep 2028, 17% at 26 May 2026; whole project close to RM2bn.
- Borneo Post, 13 Jun 2026: Sabah Southern Madani Link ensures development reaches interior, says Anwar Groundbreaking by the Prime Minister in Sipitang, 13 June 2026.
- Borneo Post, 28 Jun 2026: SSML strengthening energy security (column by an engineer) About 330 km in total; Phase 1B about 270 km from Upper Padas to Kalumpang.
- The Star, 5 May 2026: revised approval for Sabah hydro-solar hybrid (Ulu Padas) 187.5 MW hydro by 31 Dec 2030; 150 MWac floating solar by 31 Dec 2031.
- Sarawak Energy, 24 Jan 2026: energisation of the Sarawak-Sabah interconnection Power flowing since 13 Dec 2025; up to 50 MW.
- Borneo Post, 22 Sep 2025: 275kV Kolopis–Segaliud transmission line restored Landslide tower collapse on the existing East-West Link, 13 September 2025.