Loading...
📮 Get Sabah This Week free every Thursday · what is on across Sabah Subscribe →
Back to Development
🔀 For Everyone

Why Does Sabah Have So Many Power Cuts?

Last updated: 27 September 2026

Why does Sabah have so many power cuts?

According to the state energy plan, SE-RAMP 2040, Sabah has had too little spare generating capacity (a 16% reserve margin in 2021 against a 30–35% standard), only one main 275 kV line carrying power to the east coast, ageing power plants, and long rural lines with bare wires. Average outage time fell from 777 minutes in 2014 to 226 minutes by July 2026; the target is under 100 minutes by 2030.

How bad are Sabah's power cuts?

Utilities measure power cuts with SAIDI: the average minutes without power per customer per year. Sabah's has fallen a long way, but it is still well above the target.

YearAverage outage minutes (SAIDI)Source
2014777.3SE-RAMP
2021332.1SE-RAMP
2023598Chief Minister, Sep 2026
2024207SESB, May 2025
July 2026226Chief Minister, Sep 2026
Target, end 2030below 100SE-RAMP
ℹ️ Why the numbers jump around

SAIDI has been counted in different ways. SE-RAMP says major incidents, such as a whole power station or a transmission line tripping, were left out of the figures before 2021 and included from 2021. Figures from SESB and the state government since then do not always match. The long-run trend is more reliable than any single year.

SE-RAMP separates two kinds of cut. Wide-area blackouts come from faults or "trippings" at power stations and on the high-voltage transmission lines. Local cuts come from the distribution network in towns and villages; they affect fewer people but happen more often.

Reason 1: not enough spare power

The reserve margin is spare generating capacity above peak demand. With a healthy margin, when one plant trips another takes over. SE-RAMP says Sabah's fell from 36.0% in 2016 to 16.0% in 2021, against an industry standard of 30% to 35%. The state government reported 8% for 2024, 19% in August 2026 and an expected 26% by the end of 2026.

A thin margin has a second effect: plants cannot be taken offline for maintenance, because there is nothing to cover for them. SE-RAMP says ageing plants have been kept running past their productive life, and delays to new plants made this worse.

Reason 2: one main line to the east coast

Sabah's west and east coasts are divided by a chain of mountains that includes the state's highest peaks. Sabah's gas is concentrated on the west coast, and the east coast relies on power sent from the west to cover its shortfall. The two halves are joined mainly by the 275 kV Kolopis–Segaliud line, the East-West Link, which SE-RAMP calls a security risk in critical need of reinforcement.

What that means in practice: on 13 September 2025, a transmission tower on the Kolopis–Segaliud line collapsed in a landslide. SESB sent 27 mobile generator sets to Beluran, Kinabatangan, Sandakan, Semporna, Tawau, Lahad Datu and Telupid. The first circuit was reconnected on 17 September and the second on 21 September.

The planned fix is a second route, the Southern Link, running from Mengalong near Sipitang through Upper Padas to Tawau, so that the east coast is no longer fed by one line.

Reason 3: old plants and long rural lines

SE-RAMP blames Sabah's high local outage rate on a distribution network of bare conductors and long lines reaching a dispersed population, and on SESB's weak finances in the past, which limited investment. SESB's plan is to replace them with insulated aerial bundled cable, starting in the areas with the most outages.

The plan also says RM2.295 billion of grid projects were built through the Sabah Special Project Planning and Delivery Unit (SAPADU), but long delays held back their benefits; with most of them completed or nearly completed, it expected the grid to improve. It estimates another RM2 billion is needed for transmission and distribution, including the Southern Link.

What is being done, and is it working?

FixWhat it doesStatus as of September 2026
Segaliud–Dam Road line upgrade to 275 kVMore power from Sandakan side to Lahad Datu, Kunak and SempornaSESB said in March 2025 it would double transfer to the east coast from 200 MW to 400 MW, with operation from April 2025; we have not found confirmation of completion
Power from SarawakExtra supply into the west of the gridLive since 13 December 2025, up to 50 MW (see power plan)
Lahad Datu battery storageFast backup on the east coast when plants trip100 MW / 400 MWh inaugurated 12 December 2025
New solar and hydroMore capacity, less gas450 MW solar programme under way; Upper Padas hydro due end 2030
Southern LinkA second 275 kV route to the east coastPhase 1A 17% built (May 2026), due September 2028; Phase 1B not yet dated

SESB's own transformation plan set an interim target of 150 minutes SAIDI by 2025 and below 100 minutes by 2030 (SE-RAMP, p.69). Status as of September 2026: we have not found a published figure for 2025; the latest figures, 207 minutes for 2024 and 226 minutes as of July 2026, are above the 2025 interim target.

Frequently asked questions

Q Why does Sabah have frequent blackouts?
The state energy plan, SE-RAMP 2040, gives four main reasons: too little spare generating capacity (a reserve margin of 16% in 2021 against a 30% to 35% standard), a single 275 kV line carrying power from the west coast to the east coast, ageing power plants kept running past their design life, and long rural distribution lines with bare conductors.
Q What is SAIDI?
SAIDI (System Average Interruption Duration Index) is the average number of minutes of power cuts a customer experiences in a year. Sabah's was 777.3 minutes in 2014 and 332.1 minutes in 2021, according to SE-RAMP. The Chief Minister reported 226 minutes as of July 2026. The target is below 100 minutes by the end of 2030.
Q Why does the east coast lose power when there is a problem near Kota Kinabalu?
Because most of the east coast's shortfall is supplied from the west coast through the 275 kV Kolopis–Segaliud line. When that line trips, as it did after a tower collapsed in a landslide on 13 September 2025, the east coast loses a large share of its supply at once.
Q When will Sabah's power cuts stop?
The official target is average outage time below 100 minutes a year by end 2030, and a reserve margin of 30% to 35%. The state government reported a reserve margin of 19% in August 2026 and expected 26% by the end of 2026. Local faults will never disappear entirely, but wide-area blackouts should become rarer as spare capacity and a second east coast line are added.
Sources & References 11 sources

Last verified: 27 September 2026

📰 Latest status

📮 Free Weekly Newsletter

Get Sabah This Week, free every Thursday

One short email a week on what's happening around Sabah: events, food, and local life. Free to join, and free to leave whenever you like.

One email a week. Unsubscribe anytime. See what’s inside →