Pan Borneo Highway Sabah: Route, Phases & Cost Explained
What is the Pan Borneo Highway in Sabah?
The Pan Borneo Highway is a 706 km trunk road across Sabah costing RM24.889 billion. It links the Sarawak border at Sindumin to Tawau, passing Kota Kinabalu, Sandakan and Lahad Datu. Phase 1A was 87.86% complete on 22 July 2026 and targets mid-2028; both phases together target the fourth quarter of 2030.
What is the Pan Borneo Highway?
The Pan Borneo Highway (Lebuhraya Pan Borneo) is one of the largest infrastructure undertakings in East Malaysia, designed to create a continuous, modern trunk road spanning the island of Borneo. The Sabah stretch is the portion of that wider network that runs entirely within the state, and it represents a major upgrade over the patchwork of older roads that previously linked Sabah's main towns.
Within Sabah, the project covers 706 km of carriageway at a total cost of RM24.889 billion. Rather than building entirely new alignments everywhere, the programme widens, straightens and upgrades existing corridors while adding new sections where terrain demands. The result is a higher-capacity route built to consistent engineering standards, intended to carry both heavy freight and everyday passenger traffic for decades to come.
📊 Want the latest numbers only? See the Pan Borneo progress tracker, updated as new figures are given in Parliament.
For a state where towns are separated by long distances and rugged interior terrain, a reliable cross-state highway is a foundational piece of infrastructure. It connects the west coast administrative centre of Kota Kinabalu with the east coast commercial towns, shortening journeys that have historically taken the better part of a day.
The route across Sabah
- Sindumin
- Beaufort
- Papar
- Kota Kinabalu
- Telupid
- Sandakan
- Lahad Datu
- Tawau
706 km in all. Phase 1B also includes branch corridors to Kudat and Ranau (see the phase board below).
The Sabah stretch begins at Sindumin, on the Sabah-Sarawak border, where it ties into the wider Pan Borneo network. From there it travels north and east, threading through the populated west coast before swinging across the interior toward the east coast districts.
Along the way the highway passes through or near several of Sabah's most important towns:
- Kota Kinabalu — the state capital and main west coast hub.
- Sandakan — a major east coast commercial and port town.
- Lahad Datu — a key agricultural and industrial centre on the east coast.
The corridor finally reaches its eastern terminus at Tawau, near the southern end of Sabah's east coast. By linking Sindumin to Tawau in a single upgraded route, the highway stitches together the west coast, the interior and the east coast into one continuous land connection.
The Sabah stretch is designed to function as a seamless extension of the Sarawak section. Drivers crossing at Sindumin continue onto the same upgraded highway standard, making overland travel across Borneo far more practical than before.
How the project is phased
Because of the scale of the works, Phase 1 is delivered in two sub-phases across 35 work packages. Splitting the programme this way lets construction begin on priority sections while later, more complex stretches are designed and procured. Packages open individually as they finish, rather than the whole corridor opening at once.
| Phase | Length | Packages | Cost | Target completion |
|---|---|---|---|---|
| Phase 1A | 318 km | 16* | RM10.9 billion | Mid-2028 |
| Phase 1B | 388 km | 19 | RM13.989 billion | Q4 2030 (with 1A) |
* 16 is the count the Deputy Works Minister gave on 14 July 2026, the most recent official figure, and matches the Auditor-General's total of 35. Statements earlier in 2026 gave 15 (Daily Express, Bernama, checked 7 October 2026).
Together the two sub-phases make up the full RM24.889 billion investment, a figure the Deputy Works Minister gave in July 2026 (Daily Express, checked 7 October 2026). Phase 1A carries the west coast trunk from Sindumin up to the Kota Kinabalu area, plus three detached packages on the east coast. Phase 1B covers four separate corridors — Kota Belud to Kudat, Telupid to Ranau, Lahad Datu to Sandakan, and Tawau to Lahad Datu.
Phase 1A 2
318 km · RM10.9 billion · 87.86% overall (22 July 2026) · target mid-2028
- West coast trunk: Sindumin to the Kota Kinabalu area
- Three detached packages on the east coast
Phase 1B 4
388 km · RM13.989 billion · 13.56% overall (January 2026) · target Q4 2030
- Kota Belud – Kudat
- Telupid – Ranau
- Lahad Datu – Sandakan
- Tawau – Lahad Datu
Phase 2 1
Planning only · no funding or timeline
- Tamparuli – Ranau About 98 km
Phase 3 1
Planning only · no funding or timeline
- Kimanis – Keningau – Kalabakan – Tawau About 432 km
Source: Deputy Works Minister, July 2026; Sabah State Assembly, November 2024. Checked 7 October 2026
Two further phases exist beyond Phase 1, both still at planning stage with no funding and no timeline: Phase 2 covering the Tamparuli–Ranau alignment of around 98 km, and Phase 3 running Kimanis–Keningau–Kalabakan–Tawau over around 432 km. Both were set out by Deputy Chief Minister Shahelmey Yahya in the State Assembly in November 2024, with implementation dependent on government approval and financial capacity.
Construction progress
Progress varies sharply between the two phases, reflecting their different start dates and scope.
As at January 2026, the figures given to the Dewan Rakyat on 26 February 2026 were (RTM, checked 7 October 2026):
- Phase 1A — 86.6% complete against a scheduled 97.55%, roughly 11 percentage points behind. On 22 July 2026 the Deputy Works Minister told the Dewan Negara it had reached 87.86% and now targets mid-2028 (RTM, checked 7 October 2026).
- Phase 1B — 13.56% against a scheduled 19.6%, around 6 points behind. No newer figure against schedule has been published. Both phases together now target the fourth quarter of 2030.
Four packages had been completed by 31 December 2023: Donggongon–Papar, Kampung Lot M to Mile 32 in Sandakan, Tawau–Semporna, and the Lahad Datu Bypass (NST). In May 2026 the Deputy Works Minister said nine more Phase 1A packages would be completed during 2026, including two on the Putatan–Menggatal route around Kota Kinabalu due to open from July, with four more in 2027. Across Phase 1 it expects 12 packages to be completed in 2028, three in 2029 and the final three by 2030 (Bernama, checked 7 October 2026).
The Auditor-General's Report 2/2026, published on 5 October 2026, found that as at 31 March 2026 only those four of the 35 packages were complete; 13 were behind schedule, nine ahead, and nine classed as problem projects (The Edge, checked 7 October 2026).
- Phase 1A 86.6% of 97.55% planned 318 km. Reported 87.86% on 22 July 2026; no newer figure against schedule.
- Phase 1B 13.56% of 19.6% planned 388 km.
Where it was scheduled to be
Source: Deputy Works Minister, Dewan Rakyat, 26 February 2026. Checked 7 October 2026
- Nov 2024 Target: first quarter of 2026 Stated November 2024.
- Oct 2025 Target moves to March 2027 Stated October 2025.
- Feb 2026 Target: first quarter of 2027 Dewan Rakyat, 26 February 2026.
- Jul 2026Now Target moves to mid-2028 Dewan Negara, 22 July 2026. Both phases together: fourth quarter of 2030.
Source: RTM; Bernama; parliamentary answers. Checked 7 October 2026
A completion figure on its own can mislead. Phase 1A being 86.6% done sounds close to finished, but it was supposed to be 97.55% done by that date. The target has slipped from the first quarter of 2026 (stated November 2024) to March 2027 (October 2025), the first quarter of 2027 (February 2026) and now mid-2028 (July 2026). Progress figures on this project change at almost every parliamentary sitting, and officials sometimes quote numbers that conflict. Always check the date attached to a figure. Figures checked 7 October 2026.
What the 13th Malaysia Plan says: the federal plan for 2026–2030 records that only four of the 35 work packages in Sabah had been completed as at December 2024. It commits to completing the subsequent Pan Borneo packages in Sabah, the Sarawak–Sabah Link Road and the Trans Borneo Highway during the plan period, and names the Sabah Pan Borneo Highway and the Sarawak–Sabah Link Road among the projects that will underpin construction growth (13th Malaysia Plan, pp.1-17, 3-24 and 3-26). See what the 13th Malaysia Plan promises Sabah, and the new Kalabakan–Simanggaris road, which starts at Kalabakan on the planned Phase 3 alignment.
Engineering and logistical challenges
Building a continuous high-standard highway across Sabah involves significant technical and logistical hurdles, particularly in the interior where the terrain is most demanding.
Key challenges include:
- Utility relocation — power lines belonging to SESB, water pipes and telecoms infrastructure often sit within or near the road reserve and must be carefully relocated before earthworks can proceed.
- Worker and equipment shortages — in the period after COVID, securing enough skilled labour and machinery on site slowed the pace of several work fronts.
- Soft soil and terrain — stretches through interior Sabah cross soft ground and hilly, uneven terrain, which complicates foundations, drainage and embankment stability.
Each of these factors adds time and engineering effort. Utility relocation in particular must be sequenced carefully so that nearby communities are not left without services while road construction advances.
Economic impact for Sabah
The highway's value lies not just in smoother roads but in the economic activity that better connectivity unlocks. The expected benefits, as described in government statements, are:
- Logistics and trade — interior districts that were previously hard to reach become more viable for moving goods, opening them up to wider markets.
- Lower transport costs — faster, more reliable freight movement reduces the time and fuel burned shifting produce and goods across the state.
- Employment — the programme supports jobs directly in construction and indirectly across supporting industries such as materials, machinery and services.
- Land compensation — RM1.2 billion had been paid to landowners along the Phase 1 corridor by July 2026, against RM2.53 billion budgeted for land acquisition in November 2024.
Specific figures for these are widely quoted but hard to stand up. Unlike Sarawak — where the government has published a Miri to Kuching saving — no official Kota Kinabalu to Tawau travel-time figure has been released for Sabah, and no official jobs total has been published either. Where you see precise numbers for either, treat them with caution.
By tying the west coast, interior and east coast into a single dependable road network, the Pan Borneo Highway is positioned as a long-term enabler of trade, agriculture and regional development across Sabah.