Pan Borneo Highway Sabah Progress Tracker 2026: Phase 1A & 1B
Phase 1 of the Pan Borneo Highway in Sabah runs 706 km from Sindumin on the Sarawak border to Tawau, at a cost of RM24.889 billion. It is split into Phase 1A (318 km, 16 work packages, RM10.9 billion) and Phase 1B (388 km, 19 packages, RM13.989 billion). On 22 July 2026 Phase 1A was reported 87.86% complete; as at January 2026 it was 86.6% against a scheduled 97.55%. Phase 1B was 13.56% against a scheduled 19.6% as at January 2026, the most recent precise figure published. Phase 1A now targets mid-2028, and both phases together the fourth quarter of 2030. An Auditor-General's report published in October 2026 found only four of the 35 work packages complete as at 31 March 2026. The highway is toll-free and fully federally funded.
Progress percentages on this project change at almost every parliamentary sitting, and officials sometimes quote figures that conflict: in June 2026 the Works Minister described Phase 1B as under 10% complete, below the 13.56% given to Parliament in February. Every number on this page carries the date it was stated. The latest overall Phase 1A figure is from the Dewan Negara on 22 July 2026; the latest figures against schedule are from the Dewan Rakyat on 26 February 2026, as at January 2026. Figures checked 7 October 2026.
Both phases were running behind schedule — Phase 1A by about 11 percentage points, Phase 1B by about 6. No newer figure against schedule has been published; Phase 1A was reported at 87.86% on 22 July 2026.
Source: Deputy Works Minister, Dewan Rakyat, 26 February 2026 (figures as at January 2026). Checked 7 October 2026.
- Nov 2024 Target: first quarter of 2026 Stated November 2024.
- Oct 2025 Target moves to March 2027 Stated October 2025.
- Feb 2026 Target: first quarter of 2027 Dewan Rakyat, 26 February 2026.
- Jul 2026Now Target moves to mid-2028 Dewan Negara, 22 July 2026. Both phases together: fourth quarter of 2030.
Source: RTM; Bernama; parliamentary answers. Checked 7 October 2026
Project overview
The Pan Borneo Highway is the largest road project ever undertaken in Sabah. Phase 1 covers 706 km running from Sindumin, on the Sabah–Sarawak border, through Beaufort, Papar, Kota Kinabalu, Telupid, Sandakan and Lahad Datu, to Tawau in the south-east. Rather than building new alignments everywhere, the programme mostly widens, straightens and upgrades existing trunk roads, adding new sections where the terrain demands it.
For the route, which corridors fall in each phase and what the highway is for, see the Pan Borneo Highway explainer.
It is not a Peninsular-style tolled expressway. It is a federally funded trunk road upgrade, delivered as 35 separate work packages that open individually as they finish, which is why parts of the route are already in use while others have barely started.
Delivery changed hands early in the project's life. Sabah's original project delivery partner, Borneo Highway PDP Sdn Bhd, was appointed in April 2016 and terminated in September 2019, with only a small share of the work complete. The Ministry of Works now implements the project directly, with JKR Sabah as Superintending Officer. That switch is the single biggest reason the cost roughly doubled.
Phase 1A: 318 km, 16 work packages
Phase 1A carries the west coast trunk — Sindumin, Sipitang, Beaufort, Bongawan, Papar, Putatan, Kota Kinabalu, Inanam, Sepanggar and on towards Rampayan Laut — plus three detached packages on the east coast: the Tawau–Semporna junction, the Lahad Datu Bypass, and the Sandakan–Telupid stretch. It is not one continuous road, and it does not run "Kota Kinabalu to Kimanis": Kimanis is not a Phase 1A boundary at all.
Phase 1A costs RM10.9 billion. As at January 2026 it stood at 86.6% against a scheduled 97.55% (Dewan Rakyat, 26 February 2026), and on 22 July 2026 the Deputy Works Minister told the Dewan Negara it had reached 87.86%. The completion target keeps slipping: the first quarter of 2026 (stated November 2024), March 2027 (October 2025), the first quarter of 2027 (February 2026), and now mid-2028 (July 2026).
Official statements differ on the Phase 1A package count. The Deputy Works Minister gave 16 in the Dewan Rakyat on 14 July 2026, the most recent official figure, and 16 plus Phase 1B's 19 matches the 35 packages counted by the Auditor-General. Statements in February, May and June 2026 gave 15.
Each point is a figure stated publicly by a minister or the Works Ministry on that date. The points are evenly spaced but the dates are not: gaps range from one month to eleven months. Progress slowed through 2026, about 1.3 points between January and July. A separate 86.6% figure given to the Dewan Rakyat on 26 February 2026 was as at January 2026.
Source: Daily Express, Bernama, Sabah Media, Sinar Harian, Nabalu News and RTM, July 2024 to July 2026. Checked 7 October 2026.
Phase 1B: 388 km, 19 work packages
Phase 1B is the larger and later phase, covering four separate corridors rather than a single stretch:
- North-west: Kota Belud to Kudat
- Central: Telupid to Ranau
- North-east: Lahad Datu to Sandakan
- South-east: Tawau to Lahad Datu
Letters of acceptance went to 13 contractors in October 2024, with construction periods of 36 to 48 months. The allocation is RM13.989 billion, fully federally funded. As at January 2026 the phase stood at 13.56% against a scheduled 19.6% (Dewan Rakyat, 26 February 2026). The Works Ministry now targets the fourth quarter of 2030 for Phase 1B together with Phase 1A, replacing the fourth quarter of 2028 given in February.
Three of the central packages — running from Kampung Lumou Baru through Kampung Toupos and Kampung Nabutan to Ranau, some 70.2 km in total — were reported underway in April 2025.
Phases 2 and 3: still at planning stage
Beyond Phase 1, two further phases exist on paper only. Answering the State Assembly in November 2024, Deputy Chief Minister Shahelmey Yahya set out:
- Phase 2 — the Tamparuli–Ranau alignment, around 98 km
- Phase 3 — Kimanis–Keningau–Kalabakan–Tawau, around 432 km
Both are at planning stage, with implementation dependent on government approval and financial capacity. No cost estimate, contract award or start date has been published for either. Anyone quoting a budget or a completion year for these phases is guessing.
What has actually opened
The highway opens in pieces. Four packages had been completed by 31 December 2023:
- Donggongon–Papar
- Kampung Lot M to Mile 32, Sandakan
- Tawau–Semporna
- Lahad Datu Bypass
In May 2026 the Deputy Works Minister said nine more Phase 1A packages would be completed during 2026, including two on the Putatan–Menggatal route, due to open from July 2026 and giving traffic a way around Kota Kinabalu city centre. Four more Phase 1A packages are scheduled for 2027. Across Phase 1 the ministry expects 12 packages to be completed in 2028, three in 2029 and the final three by 2030. In July 2026 the ministry repeated the target of nine packages by the end of the year.
- Complete 4 of 35 Donggongon–Papar, Lot M–Mile 32 Sandakan, Tawau–Semporna, Lahad Datu Bypass
- Due in 2026 9 of 35 Phase 1A, incl. two on Putatan–Menggatal
- Due in 2027 4 of 35 Phase 1A
- Due in 2028 12 of 35
- Due in 2029 3 of 35
- Due by 2030 3 of 35
Due dates are the Works Ministry's plan, stated in May 2026. Bars show packages out of 35.
Source: NST and Auditor-General's Report 2/2026 (completed packages); Bernama, May 2026 (schedule). Checked 7 October 2026
The Auditor-General's Report 2/2026, published on 5 October 2026, found that as at 31 March 2026 only these four of the 35 packages were complete. Of the rest, 13 were behind schedule, nine were ahead, and nine were classed as problem ("sakit") projects.
What the 13th Malaysia Plan says: the federal plan for 2026–2030 records that only four of the 35 work packages in Sabah had been completed as at December 2024. It commits to completing the subsequent Pan Borneo packages in Sabah, the Sarawak–Sabah Link Road and the Trans Borneo Highway during the plan period, and names the Sabah Pan Borneo Highway and the Sarawak–Sabah Link Road among the projects that will underpin construction growth (13th Malaysia Plan, pp.1-17, 3-24 and 3-26). See what the 13th Malaysia Plan promises Sabah, and the new Kalabakan–Simanggaris road, which starts at Kalabakan on the planned Phase 3 alignment.
Why it has run late
The causes cited officially are consistent across parliamentary answers and ministry statements:
- Land acquisition — disputes and compensation have held up work fronts. Land acquisition for Phase 1 was budgeted at RM2.53 billion in November 2024, of which RM1.2 billion had been paid by July 2026.
- Utility relocation — SESB power lines, water mains and telecoms sit within the road reserve and must be moved, in sequence, without cutting off nearby communities.
- Worker and material shortages — securing labour and machinery has been difficult, particularly in the period after COVID.
- Terrain and soil — stretches through the interior cross soft ground and hilly terrain, complicating foundations, drainage and embankments.
Underlying all of it is the 2019 termination of the project delivery partner model, which required the remaining scope to be reassessed five years after the original estimate and re-procured under conventional federal contracting.
Cost and funding
Phase 1 was estimated at RM12.86 billion in 2015. It now stands at RM24.889 billion — RM10.9 billion for Phase 1A and RM13.989 billion for Phase 1B.
The Works Ministry attributes the increase to the change in delivery model, changes in scope and design, geotechnical structures and soil treatment, large-scale utility relocation, and inflation in the price of steel, bitumen, cement, machinery and labour.
The Auditor-General's Report 2/2026 gives different figures: a projected Phase 1 cost of RM18.96 billion, up from RM17.91 billion, with Phase 1A at RM11.323 billion. The published summaries do not explain how these relate to the Works Ministry's RM24.889 billion, so treat them as separate measures rather than a correction.
The project is fully federally funded. There is no state cost-share, no private concession and no toll. Phases 2 and 3 have no allocation.
The Pan Borneo Highway is toll-free, and has been a stated federal commitment since 2015. The reasoning given by the Works Minister is that unlike expressways in Peninsular Malaysia, Pan Borneo is the main route across Sabah and Sarawak with no alternative road alongside it, so there is no basis for charging. There is no concessionaire and no toll operator appointed.
Frequently asked questions
Q When will the Pan Borneo Highway be fully completed?
Q What is the total cost of the Pan Borneo Highway in Sabah?
Q Will tolls apply on the Pan Borneo Highway?
Q Can I drive the Pan Borneo Highway now (2026)?
Q What are the Phase 2 and Phase 3 details?
Q Why is the project running late?
Q Who is building the Pan Borneo Highway in Sabah?
Sources & References 23 sources
Last verified: 7 October 2026
Project Management
Official Statements
- Dewan Rakyat — cost breakdown, 14 July 2026 Deputy Works Minister on the RM12.86b to RM24.889b increase and land compensation
- Sabah State Assembly — Phases 2 and 3, 19 November 2024 Shahelmey Yahya on the Tamparuli–Ranau and Kimanis–Tawau alignments
- Phase 1 completion target, April 2025 Head of State policy address, Phase 1 by 2029. Superseded: the Works Ministry gave Q4 2030 in July 2026.
- Toll-free commitment, August 2025 Works Minister confirms no tolls on Pan Borneo
- Package openings, 13 May 2026 (Bernama) Deputy Works Minister: nine Phase 1A packages to be completed in 2026, four in 2027, 12 in 2028, three in 2029 and three by 2030; Putatan–Menggatal route to open from July 2026; gives Phase 1A as 15 packages. Checked 7 October 2026.
- Land compensation and cost, 14 July 2026 (Daily Express) RM24.889 billion Phase 1 cost (RM10.9b Phase 1A with 16 packages, RM13.989b Phase 1B with 19) and RM1.2 billion land compensation paid. Checked 7 October 2026.
- Land acquisition budget, 19 November 2024 (Bernama) RM2.53 billion for Phase 1 land acquisition (RM1.32b Phase 1A, RM1.21b Phase 1B). Checked 7 October 2026.
- Phase 1B contracts, 5 November 2024 (BusinessToday) Letters of acceptance to 13 contractors in early October 2024; 36 to 48 months. Checked 7 October 2026.
- Phase 1B central packages, 28 April 2025 (Bernama) WP33–WP35, Kampung Lumou Baru to Ranau, 70.2 km. Checked 7 October 2026.
- Four packages completed by end-2023, 11 January 2024 (NST) Papar–Donggongon, Tawau–Semporna, Lahad Datu bypass and Kampung Lot M–Sandakan Mile 32 completed as at 31 December 2023. Checked 7 October 2026.
- Auditor-General's Report 2/2026, 5 October 2026 (The Edge) As at 31 March 2026: four of 35 packages complete, 13 behind schedule, nine ahead, nine problem projects; projected cost RM18.96b. Checked 7 October 2026.
- Thirteenth Malaysia Plan 2026-2030 (Ministry of Economy) p.1-17: Sabah Pan Borneo and Sarawak–Sabah Link Road underpin construction growth; p.3-24: four of 35 Sabah work packages completed as at December 2024; p.3-26: remaining packages, Link Road and Trans Borneo Highway to be completed in the plan.
Progress figures (Phase 1A and 1B)
- Dewan Negara, 22 July 2026 (RTM) Phase 1A 87.86%; Phase 1A target mid-2028; both phases Q4 2030; nine packages by end-2026. Checked 7 October 2026.
- Dewan Rakyat, 26 February 2026 (RTM) As at January 2026: Phase 1A 86.6% vs 97.55% scheduled; Phase 1B 13.56% vs 19.6%; targets Q1 2027 and Q4 2028. Checked 7 October 2026.
- Works Minister, 10 February 2026 (Nabalu News) Phase 1A 86.98%, Phase 1B 13.68%. Checked 7 October 2026.
- Deputy Works Minister, 9 January 2026 (Sinar Harian) Phase 1A 86.53% against 96.24% scheduled. Checked 7 October 2026.
- Works Ministry, 8 October 2025 (Sabah Media) Phase 1A 84.2%; target March 2027. Checked 7 October 2026.
- Works Minister, 7 November 2024 (Bernama) Phase 1A 78%; target first quarter of 2026. Checked 7 October 2026.
- Works Minister, 29 July 2024 (Daily Express) Phase 1A 77.41%. Checked 7 October 2026.
- Works Minister, 17 June 2026 (Utusan Borneo) Described Phase 1B progress as under 10%, conflicting with the February parliamentary figure. Checked 7 October 2026.